Project Timeline

Fall 2007 – Spring 2008

  • Introduce project to public officials, landowners and other stakeholders
  • Complete environmental and cultural resource surveys
  • Submit major permit applications
  • Acquire right of way

Spring 2008 – Fall 2008

  • Construction

2009

  • Pipeline in service