Project Timeline
Fall 2007 – Spring 2008
- Introduce project to public officials, landowners and other stakeholders
- Complete environmental and cultural resource surveys
- Submit major permit applications
- Acquire right of way
Spring 2008 – Fall 2008
- Construction
2009
- Pipeline in service